How to Calculate Budgets For Agile Teams

by Jesse Fewell, 2 November 2012 | The Agile Blogosphere

This content is syndicated from LeadingAgile by Jesse Fewell. To view the original post in full, click here.

A common concern I get from Agile newbies is “how do I calculate the cost of my agile project, if I don’t do all up front planning?” Actually, it turns out that when I leverage agile methods to simplify my project accounting,  budgeting becomes much easier. I’m going to show you two approaches that leverage two powerful attributes of agile projects.

Powerful Attributes of Agile Projects

Stable Team Roster. Project managers across the world agree that a key risk for any project is getting your people yanked off the team, or having new people thrown onto a team only at the last minute. This is the evil version of “Resource Leveling”, and it prevents any reliable forecast of a project burn rate. So, let’s see what happens when we request, nay demand, a stable team roster.

Time-boxed Iterations. Rather than try to calculate the budget of a team across 12 months, I want to simplify my problem. If we work in 1-month time-boxed iterations, I only need to calculate the budget of a given iteration. Let’s see how that works below.

Approaches for Calculating Agile Team Budget

Using a Blended RateWhen I worked at Marriott International HQ outside of Washington DC, project managers did not have visibility into the people’s compensation. Instead, we used a common “blended rate” of $125/hour. HR estimated the total loaded cost of the organization came down to that one number. Let’s assume I have a team roster of 12 people, but 4 of them are half-time, yielding a total of 10 Full-Time Equivalents (FTEs).

=> $125 X 8 chargeable hours per day = $1,000 fixed burn rate per person per day.

=> $1,000 X 10 FTEs on my team = $10,000 fixed burn rate per day.

=> $10,000 X 10 chargeable days in a 2-week iteration = $100,000 fixed iteration burn rate.

Using Specific Labor CategoriesIn other organizations, the Project Manager has to capitalize labor costs according to specific categories. For that we can’t over-simplify the problem with a blended rate.

=> Annual loaded cost of each team member / number of theoretical iterations in a year = fixed burn rate per iteration for that team member

=> Sum (every team member’s specific fixed burn rate per iteration) = fixed iteration burn rate

In the example below, I run these calculations to derive a $19,350 fixed burn rate per iteration.

Sample team costs

So What?

Having a fixed, reliable iteration burn-rate is killer. Once I have that budgetary metric, I finally have some compelling talking points around common conversations:

…or use the metric to argue against common project mistakes:

What about you? Have you found agile projects to be easier or harder to budget?

 

 

The post How to Calculate Budgets For Agile Teams appeared first on LeadingAgile.